1.1 Network Diagram
The activity on node diagram is represented by the node, whereas the direction in which the activities will be fulfilled is represented by an arrow (Field and Keller). The activity on node diagram for Fencefall Limited is as follows:
1.2 Timing of activities and float time
Timing of activity:
The timing of the activities was determined by forward pass and backward pass:
Forward pass
In the forward pass method, every activity is assumed to begin right after the predecessor activity ends, thus, the early start time of the project is zero and the early finish ...