1. Scheduling - The drum and the rope (pp. 214-217). Describe this process.
The Drum and rope system are used to ensure that scheduling of jobs happens at the same pace that the bottleneck or dominant machine in the setup can handle them. The Drum ensures that a standard pace is set for all the machines, so that the throughput of all machines is synchronized to the pace of the bottleneck. When a piece of work is completed by the bottleneck, it sends a message indicating when the work was completed, thus informing the others in the assembly line ...