Question 1
Another key feature that may hinder effective launch of the project within a period of 12 weeks is that some of the activities are considered as being critical for the project leading to a situation where the management may opt to focus more on such activities. It would be important for the management to ensure that it takes caution as a way of promoting overall success when dealing with critical activities. From the list of activities, the earliest activity will be activity D, which focuses on the assembly of all the key items that would ...