dd mmmmm yyyyy
ATTN: Director, Project Support Office I have reviewed the project summary and the following are my findings and recommendations in moving forward. We are already at the midpoint and we have already accumulated a cost overrun of $59,750. Assuming that we will maintain the same performance, we will incur a total overrun of $119,500 by the end of the project. With a planned budget of $471,000 and projected actual cost of 530,750, that would be 12.7% over the budget which is too large a variance to allow. For the work done so ...