Gantt Chart and Network Diagram
Gantt chart The picture below shows the Gantt chart of Store relocation project of Hamptons: There are 14 major tasks to be completed for successful project outcomes, where, four initial major tasks are further divided into sub tasks to lead the project in flow. The first major task of initial research is divided into three sub tasks include problem identification, search for location and feasibility research. The project management decided to allocate two weeks to complete this task. The second major task of planning is directly connected with initial research task; it means that planning cannot be started until ...